Loosen the bolts at the base of the Winkie and rotate the drilling assembly to the vertical position using the bubble level. When in correct position tighten to prevent the machine from tilting during the drilling cycle.
If drilling more than one auger length, apply the stabilizer bars from the top of the assembly to the front center bar of the trailer.
Once the machine is set, the gas line is open, the gear is in neutral, and the choke is on, use the pull handle to crank the motor. (Pull two or three turns with the choke on and throttled two or three clicks, then turn choke off and crank. It should start with one or two cranks.)
Last updated by Derrick Bellamy 03/27/02